Wheatland County Committee of the Whole Brief

By Melissa Crispin-Piche Local Journalism Initiative Reporter

Wheatland County is taking a new look at how it decides which roads get paved, rebuilt or repaired as construction costs climb and traffic grows on some routes.

The committee of the whole voted Nov. 17 to have staff rewrite the county’s road construction and paving policies and bring the drafts back to council. The proposed approach would rank projects using factors such as safety, traffic volumes, road condition, connections to other routes, and the cost of maintaining a road over its lifetime.

Operations manager Cody Zimmerman said the current policy sets out no formal criteria for choosing projects. Staff already consider traffic counts, safety and operating costs, he said, and putting those factors in writing would help residents understand why one road gets work before another.

The proposal would keep a five-year program, with the first three years treated as firm so staff can line up design work, permits, land agreements and utility moves. It would also replace the paving policy with a broader surfacing policy that sets minimum requirements for work such as asphalt paving, chip seal and road oil treatments. The committee discussed what those requirements could look like. The thresholds will be part of the drafting work.

Zimmerman said the budgeting estimate for paving was about $1 million a mile in 2020. He now puts the typical figure closer to $1.6 million, with some work reaching $1.8 million a mile. He pointed to fuel, oil and labour costs.

Staff have also started work on a transportation master plan, beginning with the Highway 1 corridor west of Strathmore. Zimmerman said he hopes to develop a draft for council consideration as work continues in 2027.

Road repairs into focus

Traffic on Range Road 243 has climbed from about 400 vehicles a day to more than 600, Wheatland County’s operations manager told councillors Nov. 17. With the road due for more work, the county faces a choice between renewing the chip seal and paying more up front to pave it.

Zimmerman said the road’s last major surface work was in 2018. Crews have since done maintenance overlays to keep it going. Another chip seal is an option, he said, though heavier traffic could shorten its useful life.

“The cost will balance out over that life cycle of the pavement,” Zimmerman said.

He estimated that rebuilding the base and applying chip seal could cost roughly 50 to 60 per cent of what it would cost to rebuild and pave the road. If the pavement lasts 20 years, he said, the chip seal might have to be renewed three times in the same period.

A councillor also raised concerns about the intersection and asked whether development could help pay for upgrades. Zimmerman said the county would seek a contribution if future development proceeds along the road. The committee took no vote on how to surface Range Road 243.

Paying for environmental work twice

Putting off a road project can leave Wheatland County paying $50,000 to $100,000 to repeat environmental fieldwork, Zimmerman told the committee of the whole Nov. 17.

Zimmerman said the fieldwork is generally valid for three years. If it takes place near the end of preliminary design or early in detailed design, the county may have only about a year of room to move once the project reaches its scheduled construction date. A longer delay can also mean revisiting utility moves or land agreements.

He pointed to a project on Range Road 264 that was ready to tender in 2019 and is now slated for construction in 2027. The delay meant the earlier work had to be redone, he said.

Councillors discussed whether the county could work with other municipalities to ask for longer timelines or fewer overlapping approvals. Zimmerman said extensions can be requested, though applying takes time and money. He suggested the Rural Municipalities of Alberta could be a route for raising the issue. The committee took no vote on a lobbying proposal.

More traffic on county roads?

Wheatland County councillors want to discuss whether rural acreage development should help pay for road upgrades when the county reviews how it approves subdivisions on agricultural land.

The issue came up at the close of the Nov. 17 committee of the whole meeting. Earlier that day, the Municipal Planning Commission voted to bring rural subdivision policies to a future committee meeting. Councillors asked to include off-site levies and other fees in that discussion.

“There should be money in the acreage pot,” one councillor said, describing a road that might need paving after a dozen acreages are developed along it.

Councillors also want to revisit how the county arrived at its rules for the number of parcels in a quarter section and why some smaller lots stay in the agricultural district. The fee discussion is at an early stage. The committee set no rate and took no vote on a new charge.