Wheatland County council approved a $1.5-million increase to the Goldfinch raw water supply project budget Nov. 10, with additional costs above the original construction contract value to be recovered from the project’s surety.

The decision brings the approved budget to $3 million. Administration said the original contractor went into receivership in March, prompting the county to make a claim against its performance bond. Staff told council the surety had accepted liability and confirmed its financial commitment in writing.

The county remains responsible for its contractual costs, including change orders. Administration said the surety is responsible for covered additional costs arising from completion of the work.

The pipeline is already installed and supplying water to the developer. Much of the remaining work involves mechanical components for a connection intended to provide backup raw water to the Speargrass Water Treatment Plant.

Staff said the replacement civil construction contract came in about $500,000 above the amount originally budgeted. The mechanical and electrical work received no bids in an earlier tender round and was being retendered after its scope was adjusted.

Some councillors questioned approving additional spending authority before final prices were available.

“I’d feel way more comfortable not ball parking it and knowing the actual costs,” Deputy Reeve Scott Klassen said.

Administration explained that the county needed an approved budget before it could proceed, even where costs would ultimately be recovered. Initial expenditures would come from existing cash and investments, followed by reimbursement.

Council carried the budget increase. Final tender prices and the eventual recovery from the surety will determine how much of the additional spending authority is used.